Construction Progress

INFRASTRUCTURE AND RESERVE

Whilst civil construction has been paused at Pinnacle, we have been working with authorities and other developers in the area to deliver critical service infrastructure to enable the continued rollout of Pinnacle.

A temporary sewer pump station and its ancillary pipelines required to service Pinnacle’s future stages and nearby estates is currently under construction and progressing well. The pump station is generally now in the ground and gravity and rising main works well progressed. It is anticipated that this infrastructure will be complete last quarter 2024.

We continue to work with the City of Ballarat to provide for their delivery of one of the wetland retarding basins within the 22 hectares of parkland in Pinnacle. 

Whilst those discussions have protracted beyond initial expectations, they continue and we are hopeful that the works will be able to commence on the basin when the weather improves towards the end of 2024/early 2025.

Until that basin and a further basin to its south is delivered, we cannot proceed with the further construction/embellishment of the reserve, including the playground area. This is to avoid damage to those spaces and ensure play activities are not located within work zones, with the future playground sitting between the two wetland areas.

The delivery of the second wetland is also subject to an amendment to the Ballarat West Development Contributions Plan, which is currently being prepared by Council and in which, unfortunately, is a lengthy process. As such, at this time, the timing is unknown. However given we now have greater certainty on the detailed design of the wetlands we are developing plans for the Pinnacle playground so as it can be delivered soon after the required drainage infrastructure is in place. 

Please rest assured that we are committed to delivering the playground when practicably possible.Further updates will be provided once available.

Stage 1 – Complete

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

STAGE 2 – COMPLETE

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

STAGE 3 – COMPLETE

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

STAGE 4 – COMPLETE

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

STAGE 5 – COMPLETE

(Lots 508 - 546)

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

STAGE 5A – COMPLETE

(Lots 501-507)

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

STAGE 6 – COMPLETE

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

COMPLETE

We are excited to see a number of dwellings under construction on this stage.

There are a few lots still available, so get in quick to secure a titled lot now and start building your dream home!

Civil Construction PhaseStatus
Bulk EarthworksComplete
DrainageComplete
SewerComplete
Water & Gas ServicesComplete
Road Boxing, Kerb & ChannelComplete
Electrical & NBNComplete
FootpathsComplete
AsphaltComplete
Signage & TopsoilComplete
Title Registration Phase 
Practical CompletionComplete
Statement of ComplianceComplete
TitlesIssued 23 Feb 2022
Inspection Phase 
ValuationAvailable
Soil TestingAvailable
 

Stage 7 - Complete

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

Stage 8 - Complete

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

Stage 9 - Complete

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

Stage 11 - Complete

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

Stage 10 - CompLete

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

COMPLETE

 

Settlements have now commenced in this stage, and we look forward to seeing house construction commenced on these amazingly located lots in the coming months.

There are still a couple of lots available in this stage, so if you are looking to build your dream home now on lots within walking distance to a great range of amenities, get in quick!

Civil Construction PhaseStatus
Bulk EarthworksComplete
DrainageComplete
SewerComplete
Water & Gas ServicesComplete
Road Boxing, Kerb & ChannelComplete
Electrical & NBNComplete
Footpaths Complete
Asphalt Complete
Signage & Topsoil Complete
Title Registration Phase 
Practical CompletionComplete
Statement of ComplianceComplete
Titles and SettlementIssued 21 July 2022
Inspection Phase 
ValuationAvailable
Soil TestingAvailable

 

 
 
 
 

Stage 7B Waterfront - Complete

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

COMPLETE

Titles have now been issued for the Waterfront release and we are excited that settlements on lots in this stage will soon commence.

For those of you wanting to build in the shorter term, there are titled prime lots still available in this stage along the future park and wetland reserve. Valuers can access the stage with prior arrangements from the civil contractor to get your finance sorted today. Don’t miss out!

Civil Construction PhaseStatus
Bulk EarthworksComplete
DrainageComplete
SewerComplete
Water & Gas ServicesComplete
Road Boxing, Kerb & ChannelComplete
Electrical & NBNComplete
FootpathsComplete
AsphaltComplete
Signage & TopsoilComplete
Title Registration Phase 
Practical CompletionComplete
Statement of ComplianceComplete
Titles and SettlementIssued 14 November 2022
Inspection Phase 
ValuationAvailable*
Soil TestingFollowing settlement or with prior Developer approval*

* Any access for soil testing must be following receipt of written developer approval if prior to settlement.