Construction Progress

INFRASTRUCTURE AND RESERVE

Whilst 2024 was a quieter year at Pinnacle given the changed market demand which saw civil construction paused, we have been working with authorities and other developers in the area to deliver critical service infrastructure to enable the continued rollout of Pinnacle once we see a shift in the market. We are hopeful that this will be in the first half of 2025 given speculation surrounding possible interest rate drops and improving market conditions.

A temporary sewer pump station and its ancillary pipelines required to service Pinnacle’s future stages along with nearby estates has been constructed.

We continue to work with the City of Ballarat to provide for their delivery of the northern wetland retarding basin within what will be 22 hectares of parkland within Pinnacle. Whilst those discussions have protracted beyond our expectations, they continue and we are hopeful that Council will be able to commence works on that basin in early 2025.

Until that basin and a further basin to its south is delivered which cater for a catchment beyond Pinnacle, we cannot proceed with the further construction/embellishment of the reserve, including the playground area. 

The future playground will sit between those two wetlands and its construction until after those works is not possible due to practicality and safety reasons (i.e. the playground area will be within the work zone buffer area required for the wetlands).

The delivery of the second wetland is also subject to an amendment to the Ballarat West Development Contributions Plan, which is currently being prepared by Council and in which, unfortunately, is a lengthy process. As such, at this time, the timing of that amendment is unknown. However given we have greater certainty on the detailed design of the wetlands we are developing plans for the Pinnacle playground so as it can be delivered soon after the required drainage infrastructure is in place.

The rollout of infrastructure and amenities in new estates needs to be done sequentially, and with the rollout of stages and unfortunately it is not possible to deliver everything in the early stages. We are however committed to delivering the playground and balance of the reserve when practicably possible, and making the Pinnacle community a welcoming and family-friendly place that residents can enjoy and be proud of.

Stage 1 – Complete

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

STAGE 2 – COMPLETE

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

STAGE 3 – COMPLETE

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

STAGE 4 – COMPLETE

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

STAGE 5 – COMPLETE

(Lots 508 - 546)

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

STAGE 5A – COMPLETE

(Lots 501-507)

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

STAGE 6 – COMPLETE

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

COMPLETE

We are excited to see a number of dwellings under construction on this stage.

There are a few lots still available, so get in quick to secure a titled lot now and start building your dream home!

Civil Construction PhaseStatus
Bulk EarthworksComplete
DrainageComplete
SewerComplete
Water & Gas ServicesComplete
Road Boxing, Kerb & ChannelComplete
Electrical & NBNComplete
FootpathsComplete
AsphaltComplete
Signage & TopsoilComplete
Title Registration Phase 
Practical CompletionComplete
Statement of ComplianceComplete
TitlesIssued 23 Feb 2022
Inspection Phase 
ValuationAvailable
Soil TestingAvailable
 

Stage 7 - Complete

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

Stage 8 - Complete

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

Stage 9 - Complete

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

Stage 11 - Complete

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

Stage 10 - CompLete

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

COMPLETE

 

Settlements have now commenced in this stage, and we look forward to seeing house construction commenced on these amazingly located lots in the coming months.

There are still a couple of lots available in this stage, so if you are looking to build your dream home now on lots within walking distance to a great range of amenities, get in quick!

Civil Construction PhaseStatus
Bulk EarthworksComplete
DrainageComplete
SewerComplete
Water & Gas ServicesComplete
Road Boxing, Kerb & ChannelComplete
Electrical & NBNComplete
Footpaths Complete
Asphalt Complete
Signage & Topsoil Complete
Title Registration Phase 
Practical CompletionComplete
Statement of ComplianceComplete
Titles and SettlementIssued 21 July 2022
Inspection Phase 
ValuationAvailable
Soil TestingAvailable

 

 
 
 
 

Stage 7B Waterfront - Complete

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

COMPLETE

Titles have now been issued for the Waterfront release and we are excited that settlements on lots in this stage will soon commence.

For those of you wanting to build in the shorter term, there are titled prime lots still available in this stage along the future park and wetland reserve. Valuers can access the stage with prior arrangements from the civil contractor to get your finance sorted today. Don’t miss out!

Civil Construction PhaseStatus
Bulk EarthworksComplete
DrainageComplete
SewerComplete
Water & Gas ServicesComplete
Road Boxing, Kerb & ChannelComplete
Electrical & NBNComplete
FootpathsComplete
AsphaltComplete
Signage & TopsoilComplete
Title Registration Phase 
Practical CompletionComplete
Statement of ComplianceComplete
Titles and SettlementIssued 14 November 2022
Inspection Phase 
ValuationAvailable*
Soil TestingFollowing settlement or with prior Developer approval*

* Any access for soil testing must be following receipt of written developer approval if prior to settlement.